Completion
Date:
April 2008
Duration:
8 Months
Work Performed
by Brandt Construction, Inc.:
35%
Project
Manager:
Meade Van Wyck
Superintendent:
Michael Manship
Owner:
Arcadia Christian Church
Project Architect:
SRS Architects
Engineer:
Weihe Engineers
References:
Patrick Kerfoot
Arcadia Christian Church
(317) 295-8638
Stu Shade
SRS Architects
(317) 844-0323 |
|

Brandt Construction, Inc. began the new construction for the
Arcadia Christian Church in August of 2007. The 15,650 square
foot wood frame, brick, and EIFS exterior structure includes a
dry sprinkler system for the existing building and wet system
for the new structure. Floor finishes included carpet, VCT, and
ceramic tile in the coffee lounge area. The town of Arcadia mandated
a new water main extension which was bored in along SR 19, with
minimal disruption to adjoining properties.
Features:
- New asphalt drive and parking area
- Extensive landscaping and site work
- Water main extension
|
| |
|
©