Completion
Date:
October 2004
Duration:
10 months
Work Performed
by Brandt Construction, Inc.:
20%
Project
Manager:
Chirag Patel
Owner:
Clear Channel Communications
Project Architect:
Luckett & Farley
Mechanical
Engineer:
Anthony Zabloudil
Civil/Structural
Engineer :
Tod Atul Mashruwala
References:
Dan Metler
Clear Channel Communications
(317) 843-8450
Jack Sugars
Luckett & Farley
(502) 585-4181
|
|
In
the summer of 2003, Brandt Construction, Inc. was selected as
the General Contractor on the Clear Channel Communications project.
This 10,900 square foot addition to the existing radio broadcasting
facility included a new break room, studio space as well as extensive
sitework. Because the building remained operational during
construction, safety was a top priority. Construction began in
November of 2003. Harsh weather conditions threatened to
delay the project, however, the project was completed in 10 months.
Features:
- New staff breakroom

- Extensive electrical work
- Construction was completed while the building was fully operational.
|
| |
|
|
©
2003 Brandt Construction, Inc. ° 330 East Saint Joseph Street
° Indianapolis, Indiana 46202
Telephone (317) 638-3300 ° Fax (317) 633-6671 |
|