Completion
Date:
April,
2001
Duration:
10 months
Work Performed by Brandt Construction, Inc.:
10%
Project Manager:
Harold Sattison
Owner:
Roman Catholic
Archdiocese of Indianapolis Properties, Inc.
Project Architect:
Halstead Architects
Mechanical Engineer:
Design Aire Consultants
Civil Engineer:
Engineering Associates, Inc.
Structural
Engineer:
Smith/Roberts &
Associates, Inc.
References:
Father Larry Voelker
Holy Cross Church
(317) 637-2620
Mike Halstead
Halstead Architects
(317) 684-1431
|
|
In
July of 2000, Brandt Construction, Inc. began construction on
a new school for Holy Cross Church. The project included renovation
of the former 17,000 SF two-story school most recently used for
Section 8 housing and the construction of a 19,000 SF two-story
addition with an elevator. Structure for the addition included
structural steel frame, bar joist, metal deck, and concrete floors.
Exterior finishes were brick and glass curtain wall façade
with a built-up roof. The project was completed as scheduled in
April 2001.
Features:
Upon
completion of the new school, the old two-story school was demolished
without damage to the new building just ten feet away.
- Little staging area required materials to be delivered as
needed.
- New school provides facilities for 200 kindergarten through
eighth grade students.
- New atrium gathering space allows teachers an alternative
to classroom activities.
- Sitework included a garden area, new sidewalks, recreation
area, and parking.
|
| |
|
|
©
2003 Brandt Construction, Inc. ° 330 East Saint Joseph Street
° Indianapolis, Indiana 46202
Telephone (317) 638-3300 ° Fax (317) 633-6671 |
|