Six Points Parking Facility |
Completion
Date:
November 2008
Duration:
2 months
Work Performed
by Brandt Construction, Inc.:
20 %
Project Manager:
Meade Van Wyck
Owner:
Six Points Road Developers, LLC
Project Architect:
JRA Architecture, LLC
Structural Engineer:
Smith/Roberts & Associates,Inc.
References:
Paul Meier
JRA Architecture, LLC
(317) 806-1071
Bryon
Willoughby
Six Points Road Developers, LLC
(704) 895-5350
|
|
In September 2008, Brandt Construction, Inc.
was awarded the Six Points Road Facility project. Work on this
project consisted of a precast concrete building with multiple
bays, car wash area, and office space. The installation of a canopy
drive through area with parking booths and multiple electronic
sensors for fully automated parking, completed the parking facility
that will service the new Indianapolis International Airport.
Features:
- Pre-cast concrete building installed in 5 days including
roof trusses
- Project was completed ahead of schedule
|
|
|
©
2003 Brandt Construction, Inc. ° 330 East Saint Joseph Street
° Indianapolis, Indiana 46202
Telephone (317) 638-3300 ° Fax (317) 633-6671 |
|