"Our mission is to produce quality construction, at an economical price, within a reasonable time frame. Customer satisfaction is our number one goal and is paramount to our continued success. We achieve this goal by employing highly trained managers and skilled tradesmen and by executing our work with the highest degree of professionalism and integrity."

 
St. Susanna School

 

Completion Date:
August 1995

Duration:
4 months

Work Performed by Brandt Construction, Inc.:
25%
Rough Carpentry, Finish Carpentry, Casework, Drywall, Specialties


Project Manager:
Todd Mattingly

Owner:
Roman Catholic
Archdiocese of
Indianapolis


Project Architect:
Design/Build – Pecsok, Randall, Lockwood,
VanAllen


Mechanical Engineer:
Design/Build – AirTrol

Electrical Engineer:
Design/Build – Dodd
Electric


Civil Engineer:
Design/Build

Structural Engineer:
Design/Build

References:
Jim May
St. Susanna
(317) 839-4554

Mark VanAllen
Pecsok, Randall, Lockwood, VanAllen
(317) 257-4421

 

This project consisted of three separate elements. The first was the addition of a pre-engineered gymnasium/fellowship center. The second was the addition of four classrooms and new administrative offices. The third portion was renovation and expansion of the narthex for the existing sanctuary. Both the classrooms and the narthex addition were conventional construction, consisting of exposed block bearing walls and wood frame roof structures.

Features:

  • Brandt Construction, Inc. was selected to provide design and build services, one of the first projects of this type for the Archdiocese of Indianapolis.
  • The entire project was built in 16 weeks, which required a great deal of up front planning and scheduling.
  • The owner provided all gymnasium floor surfaces and kitchen equipment.
  • The entire project was completed at a cost of under $50.00 per square foot.



 
 
© 2003 Brandt Construction, Inc. ° 330 East Saint Joseph Street ° Indianapolis, Indiana 46202