White River Christian
Church |
|
Completion
Date:
July, 2002
Duration:
11 months
Work Performed by Brandt Construction, Inc.:
30%
Senior Project Manager:
Chirag Patel
Owner:
White River
Christian Church
Project Architect:
BSA Design
Mechanical Engineer:
BSA Design
Civil Engineer:
BSA Design
Structural Engineer:
BSA Design
References:
Stu Shades
White River Christian Church
(317) 844-0323
Kalevi Huotilainen
BSA Design
(317)819-7878
|
|
The
White River Christian Church project was a 43,000 square foot
building addition that now houses classrooms from preschool to
fifth grade, a choir stage, dressing rooms, a baptistry, a coffee/lounge
area, meeting spaces, and a renovated kitchen. Along with the
addition, there is extensive sitework including sidewalks, curbs,
landscaping, parking lots on three sides, and a detention pond.
Brandt Construction, Inc. was selected as General Contractor for
this project in August of 2001 after competitive bidding. We negotiated
the addition of an additional classroom wing and associated sitework.
The project plus the additional classroom wing was completed within
the original schedule.
Features:
A
1,000 - 1,200 seat sanctuary with theatrical lighting and sound
system.
- Project was completed in 11 months, without interrupting
any daily activities.
- Project added 11 additional classrooms.
- The building is fully sprinklered.
|
| |
|
|
©
2003 Brandt Construction, Inc. ° 330 East Saint Joseph Street
° Indianapolis, Indiana 46202
Telephone (317) 638-3300 ° Fax (317) 633-6671 |
|