Project
Manager:
Todd Mattingly
Assistant
Project Manager:
Nick Taphorn
Owner:
Roman Catholic Archdiocese of Indianapolis
Project Architect:
CSO Architects
|
|

Project Name: St. Gabriel
Catholic Church
Project Scope:Brandt Construction, Inc. has
begun construction for the renovation and church addition at St.
Gabriel Catholic Church. The project consists of constructing
a steel framed tower addition to the south end at the existing
Sanctuary, renovating the existing Sanctuary and transforming
the existing church office area adjacent to the Sanctuary into
a Gathering Space. The renovation consists of a new altar stage
to be built at the existing entrance to the Sanctuary, new flooring,
new storefront entrances, covering existing masonry block with
drywall at the Sanctuary, painting the existing tectum deck, modifications
to the mechanical system and new lighting in the Sanctuary and
Gathering space. Project completion is anticipated to be at the
end of October 2010.
Project Status: Set structural steel last week.
Begin metal stud framing this week. Saw cut for A/U rough-ins
and perfrom underslab rough-ins. Pour back interior slab cuts
in Sanctuary and Gathering.
Page last updated on August 10,
2010